試題內(nèi)容

You have just finished most of the work on a new system integration project when the seller comes to you with detailed procedures for close out of the contract. The contract included closeout procedures. What should the project manager do?
A、 Revise the closeout procedures after getting management’s approval.
B、 Get a change order.
C、 Create new procedures that are more complete.
D、 Assess the quality of the seller’s new detailed procedures and if they are better than the current procedures.use them.