試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager discovers an unpredictable high-impact risk has become a factor in the project. self-interest among team members is keeping the issue from being reached, The project manager must act quickly to refocus the team and get the project on tack. which of following techniques should the project manager use to resolve the issue?
A、Compromise
B、Collaborate
C、Force
D、Accommodate