Three weeks into a construction project, a contractor encounters an underground water pipe which was not included in the contract. They are verbally instructed by the customer's representative to divert the water pipe around the construction site .What should the contractor do next?
A、Divert the water pipe as instructed
B、Submit a change request
C、Analyze the impact of the change
D、Submit a claim