色戒完整版播放|色戒完整版未减版时间|反击电影在线观看免费完整版中国|风月奇谭未删减完整版在线观看,色婷婷综合视频,午夜1区,雏妓电影未删减完整版在线观看国语

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager presents deliverables to the customer for approval. The customer claims that the deliverables do not meet the acceptance criteria, and asks the project manager to rework the deliverables. The customer also wants to access the information regarding the progress of the rework. Which activity should the project manager execute next ?
A、Configuration identification
B、Configuration status account
C、Configuration control
D、Configuration verification and audit


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容